Profile of YOUNG INDIA CONSTRUCTION PVT.LTD, JAMSHEDPUR

Updated   Not Updated    Profile     Back    

Forest & NPV Clearance

Forest Clearance
Application Detail
Application No. 1188 Date 18 Apr 2016 Area 0.000
Forest Land Details
Reserve (HA) 0.000 Village (HA) 0.000 KHESHRA (HA) 0.000
DLC (HA) 0.000 Protected (HA) 0.000 Jhati Jangal(HA) 0.000
Other (HA) 0.000
Non-Forest Land Details
Private (HA) 3.540 Govt.. (HA) 0.000    
Stage 1 Clearance Letter No. 1829/JAMSHEDPUR  Date 25 May 2016 View File View File
Stage 2 Clearance Letter No. NA  Date -- View File View File
Valid Upto. -- 
     
Forest Clearance
Application Detail
Application No. 1188 Date 18 Apr 2016 Area 3.540
Forest Land Details
Reserve (HA) 0.000 Village (HA) 0.000 KHESHRA (HA) 0.000
DLC (HA) 0.000 Protected (HA) 0.000 Jhati Jangal(HA) 0.000
Other (HA) 0.000
Non-Forest Land Details
Private (HA) 3.540 Govt.. (HA) 0.000    
Stage 1 Clearance Letter No. 1829/JAMSHEDPUR  Date 25 May 2016 View File View File
Stage 2 Clearance Letter No. NA  Date -- View File View File
Valid Upto. -- 
     
Forest Clearance
Application Detail
Application No. 1188 Date 18 Apr 2016 Area 3.540
Forest Land Details
Reserve (HA) 0.000 Village (HA) 0.000 KHESHRA (HA) 0.000
DLC (HA) 0.000 Protected (HA) 0.000 Jhati Jangal(HA) 0.000
Other (HA) 0.000
Non-Forest Land Details
Private (HA) 0.000 Govt.. (HA) 3.540    
Stage 1 Clearance Letter No. 1188  Date 20 Apr 2016 View File View File
Stage 2 Clearance Letter No. 1829  Date 25 May 2016 View File View File
Valid Upto. 26 Sep 2027 
     

NPV Paid

No Records Found

NPV Arrear

No Records Found

NPV Refund

No Records Found